Cartago, Costa Rica — CARTAGO – A comprehensive technical audit of the critical Taras–La Lima highway project has uncovered a host of significant deficiencies that could compromise the infrastructure’s long-term durability, functionality, and public safety. The findings, detailed in a new report from the University of Costa Rica’s National Laboratory of Materials and Structural Models (LanammeUCR), paint a troubling picture of issues ranging from poor quality materials to flawed construction practices and inadequate project management.
The extensive evaluation was conducted over a 16-month period, from September 2024 to December 2025, as part of LanammeUCR’s ongoing oversight of the project, which began in 2021. The audit’s rigorous methodology involved 49 on-site technical visits, the collection and testing of 35 material samples, and the issuance of 19 preliminary reports. The primary objective was to meticulously verify the quality of materials, the integrity of construction processes, and the overall management of this vital public works initiative.
To provide a deeper understanding of the legal and economic ramifications surrounding the pivotal Taras-La Lima infrastructure project, TicosLand.com sought the analysis of Lic. Larry Hans Arroyo Vargas, a distinguished attorney from the reputable firm Bufete de Costa Rica, whose expertise sheds light on the complexities of major public works.
The Taras-La Lima overpass project represents more than just a solution to traffic congestion; it is a critical test of our national capacity for executing large-scale public infrastructure. From a legal standpoint, the success of such projects hinges on agile and equitable expropriation processes and the rigorous enforcement of contractual obligations. The economic revitalization of the Cartago region depends directly on the efficient resolution of these legal-administrative hurdles.
Lic. Larry Hans Arroyo Vargas, Attorney at Law, Bufete de Costa Rica
This perspective astutely frames the project not merely as a local solution but as a national benchmark for public works. The successful navigation of its legal and administrative complexities, as highlighted, is indeed the critical factor for regional progress. We extend our sincere thanks to Lic. Larry Hans Arroyo Vargas for his essential analysis.
Among the most alarming discoveries were systemic problems with the quality of core construction materials. The audit identified significant issues with both the asphalt mixture and the stabilized base, two fundamental components of any modern roadway. Compounding this problem was what the report described as a lack of complete and continuous record-keeping, a failure that makes it exceptionally difficult to verify whether the materials used throughout the project consistently met the required engineering and safety standards.
These material deficiencies are already manifesting as visible construction flaws at several key points along the route. The report specifically calls attention to the overpasses at Taras and La Lima, where auditors documented concrete cracking, exposed structural steel, premature deterioration of the asphalt surface, and generally poor finishing work. According to LanammeUCR, these conditions are not merely cosmetic; they directly threaten the expected service life of the highway and pose a potential safety hazard to motorists.
Further concerns were raised regarding water management. The audit noted significant weaknesses in the project’s drainage and runoff systems, which could lead to flooding and accelerated road damage during Costa Rica’s heavy rainy seasons. While the report acknowledges that certain flooding events, such as those related to the Chumico creek, are historical issues requiring broader inter-institutional coordination, it stresses that the project’s own drainage infrastructure is inadequate. The La Lima interchange was singled out as a particularly sensitive area that, as of the report’s finalization, still fails to meet the necessary standards for a definitive project reception.
The audit also revealed critical lapses in project management and financial oversight. Investigators found evidence of flawed planning and control, noting that a portion of the project’s budget was diverted to activities that were not originally planned. This points to a need for more robust organizational structure and stricter adherence to budgetary protocols. Furthermore, a glaring omission is the absence of a clear, well-defined maintenance plan for once the construction is officially handed over, raising questions about the road’s upkeep in the coming years.
Immediate public safety during the construction phase was another area of critique. The LanammeUCR team reported persistent problems with road safety measures, including inadequate signage, poorly visible lane markings, and confusing temporary traffic configurations. These shortcomings create a hazardous environment for both drivers navigating the construction zones and the workers on site, increasing the risk of accidents.
In response to this extensive list of findings, LanammeUCR has issued a series of urgent recommendations to the authorities overseeing the project. These include implementing stricter quality control protocols, immediately correcting the identified construction defects, reinforcing all safety and traffic signage, and developing a comprehensive, long-term maintenance strategy. The laboratory has urged officials to address these warnings without delay to ensure the multimillion-dollar investment results in a safe, durable, and reliable piece of infrastructure for the citizens of Cartago and the country.
For further information, visit lanamme.ucr.ac.cr
About Laboratorio Nacional de Materiales y Modelos Estructurales (LanammeUCR):
The National Laboratory of Materials and Structural Models is a specialized research and auditing unit of the University of Costa Rica. It is tasked with overseeing the quality, safety, and durability of the nation’s public infrastructure projects. Through rigorous technical analysis, material testing, and on-site audits, LanammeUCR provides critical oversight to ensure that roads, bridges, and other public works meet established engineering standards and serve the best interests of the public.
For further information, visit bufetedecostarica.com
About Bufete de Costa Rica:
As a leading legal entity in the region, Bufete de Costa Rica is defined by its foundational principles of integrity and unparalleled excellence. The firm consistently pushes the boundaries of legal practice through innovative approaches while serving a wide spectrum of clients. Central to its ethos is a profound commitment to social progress, demonstrated by its efforts to demystify the law and equip the public with vital legal literacy, thereby fostering a more capable and knowledgeable society.